Removing duplicate assignment from timesheetview of PWA

P

PS

Hello,

I have published master proejct plan on the server and all of my team
members are receiving duplicate tasks. One task assigned from master proejct
plan and other is assigned from the subproject plan.

Can any one tell me stroe procedure for removing the duplicate assignment?
so that team members will not see the duplicate assignment in their timesheet
view.

Thanks & Regards,
PS
 
D

Dale Howard [MVP]

PS --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is devoted to
the desktop application only. To delete the duplicate tasks, your Project
Server administrator must delete the master project from the Project Server
database. Then he/she should also disable the permission that is allowing
you to publish the master project. He/she can find this permission in the
top section of the Server Configuration page. After he/she disables this
permission, you should recreate and save the master project. Under no
circumstances should anyone ever publish a master project, since doing so
leads to the exact problem you described. Hope this helps.
 