HI All - I hope this isnt too much of a newbie question. I have been using
project for a long time but am now taking it to a whole new level.
Basically we are doing a roll out to ~150 different entities and locations.
The rollout model is identical at all locations, but will have consecutive
end-to-start relationships between all tasks. I have entered all rollouts as
subprojects so I have 150 seperate files on disk in addition to the Master.
My question is this: When I make a change to the rollout model I currently
have to change 150 subprojects/files. Is there anyway to organize this
project so I can make a single common change to all 150 subprojects?
project for a long time but am now taking it to a whole new level.
Basically we are doing a roll out to ~150 different entities and locations.
The rollout model is identical at all locations, but will have consecutive
end-to-start relationships between all tasks. I have entered all rollouts as
subprojects so I have 150 seperate files on disk in addition to the Master.
My question is this: When I make a change to the rollout model I currently
have to change 150 subprojects/files. Is there anyway to organize this
project so I can make a single common change to all 150 subprojects?