Hello All,

I'm looking for some specific values from Project to help me with my
weekly reporting needs. I'm wondering if Project has a report that
will provide me with this detail:

(1) Cumulative # Tasks with Planned Completions by a specifed date
(i.e. 40 by 09/20/05, 90 by 10/03/05, etc.)
(2) Actual # of Tasks completed by a specified date
(i.e. 30 by 09/20/05, 70 by 10/03/04, etc.)
(3) Cumulative Number of Effort Hours Planned in a Given Week
(4) Actual Number of Effort Hours Recorded in a Given Week

Thanks!

- EHM, PMP
 
D

DonL

EHM,

Only the Project Summary report found in the Overview Reports contains the
fields you are looking for, but not summarized the way you want. I would
suggest exporting your project data to Excel and either writing a macro or
using a pivot table to accomplish your desired results, especially if you
want to have the capability to create any graphs.

Hope this helps! :)
 