Anita said:
I want to print a report to show me which tasks should have been finished
between 2 dates and then be able to print out these tasks for each individual
resource.
For example, which tasks has Fred failed to get done between 1st Feb and
28th Feb.
Any advice gratefully received. Version XP.
Thanks, Anita
Anita,
Here is one way to do what you want, there are probably a few others.
First, activate the Resource Usage view. Next, create the following
resource filter under Project/Filtered For/More Filters/New (I called
mine "Should have finished Range")
And/Or Field Name Test Value
Finish is greater than or equal to "Start of Range"?
And Finish is less than or equal to "End of Range"?
And Actual Finish equal NA
Also be sure to check the "show related summary rows" option even though
technically there are no summary rows on the Resource Usage view - the
"summary" is the resource name.
When you apply the filter you should get the data you want. I assumed
you do NOT want to see assignments in the range if they indeed are
finished. If you do, just leave out the last line of the filter.
To print out a report for each resource, you can insert page breaks
between each. You could also add the Resource Name to the filter but
then you would have to run it over and over (multiple inputs for the
dates) for each resource.
Hope this helps.
John
Project MVP