Report for Holidays

A

Anita

I don't use the individual calendars to enter holidays. Instead I enter
holidays as tasks, assign a resource and constrain the task to 'must start
on'.

I want to be able to print out all of my holiday tasks in a report - is
there any way of doing this?

Also, if I did use the individual calendars, could I print holidays from
individual or combined calendars?

Thanks

Anita
Using v2000 and v2003
 
M

Mike Glen

Hi Anita,

Welcome to this Microsoft Project newsgroup :)

You could use a Flag field and insert a Yes for holiday tasks, then filter
on that Flag. Or use the Marked field. Then print (try print preview
first).

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
A

Anita

The flag option seems to work great - thank you

Mike Glen said:
Hi Anita,

Welcome to this Microsoft Project newsgroup :)

You could use a Flag field and insert a Yes for holiday tasks, then filter
on that Flag. Or use the Marked field. Then print (try print preview
first).

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top