Hardip
Hi All
I have a reasonably large schedule handed to me. Unfortunately, the
standard calendar needs to be changed to incorporate public holidays.
The schedule has a number of items where the % completes are updates,
resources are assigned into each tasks and its being kept up-to-date on a
daily basis.
In updating the standard calendar for the schedule I don't want to break it,
as this will take a long time to determine the individual errors.
Any help and assistance would be appreciated.
Regards, H