Report

T

Trisha

Is there an easy way in Project 2003 or Project 2007 to create a report with
the following information?

Resource, Task, hours (hours resource posted against task)

Thanks!
 
D

Dale Howard [MVP]

Trisha --

How about using the default Who Does What When report, but customize it by
changing Work to Actual Work? If necessary, you could also change the
Column value from Days to Weeks. Hope this helps.
 