This question was asked a week ago by "Deluth" with no
response. I would love to know the answer to this
question! Can anyone help?

I have all my resources in a Resource Pool. I update
vacation/holidays/etc.. in this pool. Can someone show me
how I can run a report to extract all the vacations from
the pool? Vacations or time off, to me, would mean that
it's any non-working time that is "different" than the
standard/project non-working time. The standard calendar
already has all the company's scheduled holiday, there's
no need to get that. The report I ran had the calendars
for all resources. This didn't help me because I had to
comb through it to find the days that were different than
the standard to count it as requested time off.
 
J

Jan De Messemaeker

Hi Diane,

This is only possible with a VBA procedure.
Even then, generating a "report" will be tough.
I once wrote a procedure finding all nonworking days for each resource, and
for each date generating a task in an other MSP file.
A summary task at resoruce level would then show absences graphically.
HTH
 