Reset Priority?

R

regattagirl

Is there a way to reset priorities back to all tasks being 500?

OR

Is there a way to easily find which tasks has priorities on them?

Thanks,
regattagirl
 
J

JackD

Select all tasks by clicking in the upper right corner(where the task number
column and the column headers intersect) or dragging a selection.
Hit the shift key and F2 at the same time - the task information box will
come up.
On the general tab of the task information dialog box enter 500 in the
priority box. Click OK.
 
R

regattagirl

Great! Thanks!

JackD said:
Select all tasks by clicking in the upper right corner(where the task number
column and the column headers intersect) or dragging a selection.
Hit the shift key and F2 at the same time - the task information box will
come up.
On the general tab of the task information dialog box enter 500 in the
priority box. Click OK.

--
-Jack ... For project information and macro examples visit
http://masamiki.com/project
or http://zo-d.com/blog/index.html
..
 
J

JackD

Glad to be of help. Just be careful what else you edit when you have that
dialog box open. Changes there are made to all tasks.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top