We have a Project where we are not tracking resource cost, only fixed cost.
However, we used to have wages associated with resources and that meant that
our costs and our EV calculations starting taking those costs into account.
When we realized this we put resource costs, past and present, on zero.
However the actuals that were entered with these data cannot be changed. How
can we reset those numbers, to make the resource cost of our project zero
again?