Thanks, John, for the assistance. You're very perceptive on the 4/1/2005
and
1/4/2005. The actual dates aren't US vs European. In rechecking the
template the Start date for Task #1 is "Thu 1/1/04" (originally) and my
Start
date for the project is "4/4/2005.
I have changed the dates via Adjust Dates. This DOES change each of the
Task dates but to some relationship I'm not too sure of. Here's what's
happening:
1) When I put a date in via Adjust Dates of 1/4/2005, the first task start
date resets to "Thu 1/1/04". [I'm using US date format of mm/dd/yy.]
2) When I put a date in (via Adjust Dates) of "03/19/2005" (today) I get a
Start date for the first task of "Wed 3/17/04". It appears to be
adjusting
for weekends and holidays (not sure, though) but why a YEAR and THREE
months
earlier?
These two examples are without any other changes, to my knowledge, to the
Project settings or changing the Start date for the project from
"4/1/2005"
as I indicated in the initial post. [Obviously, changing the Adjust Dates
date does change the Project Start date when I'm on Task #1].
Relative to your comments...
A) When you commented about the calculation being automatic I'm not
following you. I checked help but Help didn't give me the insight I
needed
to check this. Where and how can I check this out?
B) All the Tasks that I checked (about 5+) has "NA" for the Constraint.
Hence, I'm concluding that this isn't the issue unless you believe
otherwise.
C) All Tasks have a variety of Start dates (Thu 1/1/04 is for the 1st 4
Tasks and then Task #5 is Fri 1/2/04, Task #6 is 1/9/04). I realize that
the
specific dates may not be meaningful but the fact that the dates DO change
is.
Obviously, I'm still lost in space but thanks for your help!
TIA,
Tom
John said:
Tom,
Curiously you mention at Start Date of 4/1/2005 and later a date of
01/4/2005. Is that just a European versus American setting (i.e. is one
date April 1, 2005 and the other Jan 4, 2005 or are they both April 1,
2005)?
If the dates are different, there are several reasons the dates on the
tasks are not shifting with the Project Start date. First, is
calculation set to "automatic"? Second, do the tasks you expect to move
have a constraint (e.g. Start No Earlier Than)? Third, is there progress
on the tasks (i.e. is the Actual Start something other than "NA"). Any
one one of those things could cause dates not to move.
Hope this helps.
John
Project MVP