A
Adrian
I am a trying to schedule a set of experiments (I'm a Ph.D. student--
cancer cell biology). The issue I have is that the experiments do not
always finish on the date anticipated. Some finish early, some finish
late. If I mark a task as 100% complete Project 2007 does not change
the finish date to the date on which the task was actually completed.
This creates a tracking issue as there are many downstream
dependencies from this first task as well as chains of dependencies
which start with this first task.
Does anyone have some suggestions on how to model/manage a project
where the dates are very fluid? Is the only way but to go in and
manually change the finish dates (I thought setting hard start and
finish dates was not a good way to use Project)?
Thanks,
Adrian.
cancer cell biology). The issue I have is that the experiments do not
always finish on the date anticipated. Some finish early, some finish
late. If I mark a task as 100% complete Project 2007 does not change
the finish date to the date on which the task was actually completed.
This creates a tracking issue as there are many downstream
dependencies from this first task as well as chains of dependencies
which start with this first task.
Does anyone have some suggestions on how to model/manage a project
where the dates are very fluid? Is the only way but to go in and
manually change the finish dates (I thought setting hard start and
finish dates was not a good way to use Project)?
Thanks,
Adrian.