H
Helen
I'm getting there - thanks to this forum!
I now have a shared resource across 3 projects (one of which is absence,
i.e. sickness & holidays!)
If I open my resource file (in resource usage view), I can see by person,
all the work that they have done across the projects in a week (to make sure
it adds up to 35 hours) then by project I can see the progression - LOVELY
But, of course, a problem remains (!), since I receive worksheets (across
the projects) by man, I would like to be able to enter the hours worked from
the resource usage view in the shared resource file, and then have that
update the hours worked in all the projects (and consequently hours remaining
etc etc) - I don't seem to be able to do this (it doesn't have any effect,
and will not save), I have to go into each project & update them individually
(which then updates the shared resource file)
I'm sure there must be a way of doing this, all help appreciated
Thanks
I now have a shared resource across 3 projects (one of which is absence,
i.e. sickness & holidays!)
If I open my resource file (in resource usage view), I can see by person,
all the work that they have done across the projects in a week (to make sure
it adds up to 35 hours) then by project I can see the progression - LOVELY
But, of course, a problem remains (!), since I receive worksheets (across
the projects) by man, I would like to be able to enter the hours worked from
the resource usage view in the shared resource file, and then have that
update the hours worked in all the projects (and consequently hours remaining
etc etc) - I don't seem to be able to do this (it doesn't have any effect,
and will not save), I have to go into each project & update them individually
(which then updates the shared resource file)
I'm sure there must be a way of doing this, all help appreciated
Thanks