Hello,
It seems that no matter what I do with the calendars, change working times,
or resource times, the first shift of every new task always starts by
scheduling 1 hour.
ex. task 1 linked to resource one which is scheduled to work from 6a to 6 p.
Upon viewing resource usage I see, for a 16 hr task:
fist day 2nd day
6 9 12 3 6 9 12 3
1hr 3hr 3hr 3hr 3hr 3hr 0 0
why would the 6-7-8 time slot only sheduled for 1hr?
It seems that no matter what I do with the calendars, change working times,
or resource times, the first shift of every new task always starts by
scheduling 1 hour.
ex. task 1 linked to resource one which is scheduled to work from 6a to 6 p.
Upon viewing resource usage I see, for a 16 hr task:
fist day 2nd day
6 9 12 3 6 9 12 3
1hr 3hr 3hr 3hr 3hr 3hr 0 0
why would the 6-7-8 time slot only sheduled for 1hr?