G
gueb
Hi!
I hope to get an answer for this one, as I got excellent ones from my other
questions.
- 2 resources in a project A and B
- B quit
- A complete a task from B in the middle of his list (so B was not there yet
in his tasks)
- B came back
Starting a task when the predecessor is not completed bring lot of confusion
in the project (force start date, predecessor star after the next job etc)
How do you handle this? I guess it is common in every project,
Do you rescheduled everything, redo your base line etc for every change?
I hope to get an answer for this one, as I got excellent ones from my other
questions.
- 2 resources in a project A and B
- B quit
- A complete a task from B in the middle of his list (so B was not there yet
in his tasks)
- B came back
Starting a task when the predecessor is not completed bring lot of confusion
in the project (force start date, predecessor star after the next job etc)
How do you handle this? I guess it is common in every project,
Do you rescheduled everything, redo your base line etc for every change?