D
Doug Carter - Sarnia, ON
I am new at MS Project and I am having difficulty utilizing calenders for
different resources in conjunction with their claendar. I need to create
different working shifts for my projects. As an example our regular shifts
are 4 - 8 Hr. Days + 4 Hrs (36 Reg. Hrs), 5 - 8 Hr Days (40 Reg. Hrs), 6 - 8
Hr. Days (40 Reg Hr. + 8
Hrs. Prem. Time) and 6 - 10 Hr. Days (8 Hrs. Reg. + 2 Prem per Day and Prem
Hrs for all of Saturday). I have been entering the premium hrs. manually
through the Window Split / Resource Work Window under O/T but this has become
very labour intensive as I have four ongoing projects with 152, 345, 86 and
600 men working on them. Is there any way to configure MS Project 2003 to
calulate these automatically. I have 16 different Trades (Resources) that
can all be working on most of the projects. I will still have to enter any
"O/T" they work but that would only be 100 - 150 manual enteries per week . .
.. instead of 1000's.
Thanks,
Douglas
different resources in conjunction with their claendar. I need to create
different working shifts for my projects. As an example our regular shifts
are 4 - 8 Hr. Days + 4 Hrs (36 Reg. Hrs), 5 - 8 Hr Days (40 Reg. Hrs), 6 - 8
Hr. Days (40 Reg Hr. + 8
Hrs. Prem. Time) and 6 - 10 Hr. Days (8 Hrs. Reg. + 2 Prem per Day and Prem
Hrs for all of Saturday). I have been entering the premium hrs. manually
through the Window Split / Resource Work Window under O/T but this has become
very labour intensive as I have four ongoing projects with 152, 345, 86 and
600 men working on them. Is there any way to configure MS Project 2003 to
calulate these automatically. I have 16 different Trades (Resources) that
can all be working on most of the projects. I will still have to enter any
"O/T" they work but that would only be 100 - 150 manual enteries per week . .
.. instead of 1000's.
Thanks,
Douglas