Resource Costs

M

Michelle

I am adding "Hotel Stay" as a Material resource in the ERP but because hotel
costs can vary, I can't work out if I have to have multiple resources with
different costs, or if I can have one resource with multiple costs that can
be selected from. can anyone advise?
 
J

John

Michelle said:
I am adding "Hotel Stay" as a Material resource in the ERP but because hotel
costs can vary, I can't work out if I have to have multiple resources with
different costs, or if I can have one resource with multiple costs that can
be selected from. can anyone advise?

Michelle,
Staying in a hotel is not a resource, it is an expense. In that regard I
suggest you put the cost for a hotel in the Fixed Cost field.

If for some reason you really want to show it as a material resource,
you could put the various rates in individual cost tables. Project
allows up to 25 date effective rates in each of 5 cost rate tables but
setting up the correct date for each stay and/or selecting the
appropriate cost rate table probably won't be as convenient as using the
Fixed Cost field - at least in my opinion.

John
Project MVP
 
M

Michelle

Hi John, thanks for that. I'm not sure either solution is totally suitable
for the process here but I will try and adapt our process somehow.
 
J

John

Michelle said:
Hi John, thanks for that. I'm not sure either solution is totally suitable
for the process here but I will try and adapt our process somehow.
Michelle,
You're welcome and thanks for the feedback.
John
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top