Is it possible to:

- To calculate cost on base of 2 different costs? I want 1 collum with
cost calculated for 50euro a hour an in the same sheet cost based on
70euro per hour (to see the difference between cost price and selling
price of a resource).

- To get a collum with the cost of the resource and in the same sheet
an collum with fixt costs per resource. Or the are woking 8 hours and
are having cost for traveling (wich i fill in at the resource) or the
dont travel but are staying in a hotel. (here i want to see the
difference between when traveling every day or stay in a hotel.
 
J

Jan De Messemaeker

Hi Jeroen,

Question 1: can be dane but only through a VBA procedure
Question 2: I'm not sure what you mean. Maybe you should post the question
in Dutch (supposing that's your mother tongue, guessing from your first
name) in microsoft.public.nl.office.project

Greetings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
G

Gérard Ducouret

Jeroen,

1st question : you could use 2 interim baselines: one for the first cost,
one for the second cost:
Tools / Tracking / set Baseline / Set interim plan
Then in any table you can insert the Baseline1 Cost and the Baseline2 Cost.
You could add a calculated field to display the difference.

Gérard Ducouret
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top