Resource Levelling

R

Rob B

Is there a way when levelling to not level tasks such as meetings where all
resources are required for the duration of the task?
 
M

Mike Glen

Hi Rob,

If you use Insert/Meeting, Project assigns a priority of 1000 and should not
level these tasks.


Mike Glen
Project MVP
 
J

JulieS

Hi Mike,

Insert meeting? Are you making a suggestion for a future release?

The funny thing is, I actually started my virtual pc and cranked up
Project 2007 to see if they changed the command from Insert > Recurring
Task to Insert > Meeting

;-)

Julie
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top