Hi Dave and John.
I would elaborate more, maybe with a different example.
The situation is as follows:
We have a basic columns, slab structure. Of this the columns and slabs
are to be cast independently. Further, each of these activities involve
form work, steel fixing and casting.
ID Task name Dur Start Finish Predecessor
7. Column 5d 01/12/06 05/12/06
8. Slab formwork 8d 03/12/06 11/12/06
7SS+2d
In totality there are 32 columns. Slab formwork work can start only
after an initial set of columns is complete, because the cast columns
are references for alignment for slab formwork.
But some basic activity of support structure for slab formwork can be
started. At the same time, this started support work on its own is of
no use, because it needs the columns (in turn the references) to be in
place in a reasonable short time after starting. So I say that after
columns have started and slab formwork starts with a lag of 2 days.
Moreover, till the entire columns are completed, the references for
entire slab formwork cannot be completed. So, in a way again the
supports for slab can be completed to a certain extent. But slab
formwork cannot be completed till all the column sets are completed.
So, in a case, where towards the end only two columns remain
incomplete, then slab formwork cannot be completed. But it does not
mean that 6 more days would be required to complete slab formwork, and
because of the supports to slab form, being in place, the activity of
slab formwork gets completed in 2 days after completion of columns.
In a way, this is important because while tracking, if I realize that
columns are delayed and only two are incomplete and if they (the
columns) take up 5 more days (finish on 10/12/06), then the slab
formwork needs to be correctly projected as delayed finish on 12/12/06,
taking 2 more days and an overall delay of 1 day in slab formwork.
Regards
Tough
tough1857 said:
Hi
Thanks for the detials on my earlier query. It really has given me a
lot of relief.
Now there is this new query which has been troubling me for quite some
time.
I have four tasks as under
ID Task Name Duration Start Finish Predecessors
5. Column 3d 01/12/06 04/12/06
6. Beam bottom 2d 04/12/06
05/12/06 5SS+2d
Now, the beam bottoms, in effect require 2 days and need to be started
after starting columns with a lag of 2 days. But at the same time, the
beam bottoms wont be completed till all columns are complete. On
conversely (in fact more correctly and realistically), the definition
of beam bottom can be as follows:
Start date: 2 days after columns start
Finish date: 1 day after all columns are completed
Duration: This would be co-related to the above said start and
finish date.
So, what the above predecessor indicates is just one definition. How do
I really define these two tasks. It is also relevant, later on during
tracking, because if the columns are delayed due to some reason, (or if
they start on time and take up more than 3 days) then the beam bottom
and column completion relation would not be indicated, which would
mislead me to believe that the beam bottoms can be completed on
baseline time in spite of columns taking more time (delayed finish
date)
I would really appreciate, if the broader picture be made clear to me
first and then followed by the finer intricacies (which indeed are
important in their own place). But then I personally like this approach
of whole to part.
ToughTough,
First, you're welcome, I'm glad we were able to help with your initial
inquiry.
I think Dave gave an excellent explanation on your latest question.
Project is not designed to handle two way constraints, which is what you
are asking. It may be possible to use a modified hammock task, but then
we've been down that road previously. As Dave suggested, the
relationship between column and beam bottom could be addressed with VBA,
but like Dave, I question if it's worth the effort.
At least that is my synopsis given the limited information provided. If
there was more detail about the relationship between "column" and "beam
bottom", a more definitive answer might be possible. For example, what
exactly is "column"? It's not a task name because it does not describe
any action to be performed and tasks in Project are action verb based
descriptions of some activity to be performed as part of a larger
overall plan. Likewise with "beam bottom". Why the 2 day delay? Is it a
"must" start 2 days later or is it a "can" start 2 days later? Why must
the beam bottom finish after the column finish? Etc.
If you think about the above questions, it could well lead to an
intuitive answer that you are able to figure out on your own. We can
help you with what Project can and can not do, but you are the only one
who really understands your particular situation and how the activities
are interrelated.
John
Project MVP