D
DaveFusion
I have two MSP plans, a Master & another.
I want to set up the Master as the resource pool, and therefore set plan 2
to use the resources from the Master.
This 'copies' the resources from Plan 2 into the Master - which is what I
want, however Plan 2 is based on a Sunday-Thursday working week ( jewish )
and the Master is standard UK ( Mon - Fri ).
When I pool my resources, the 'Resource Usage' view shows all resources on
the Jewish calendar - can I get the Resource Usage view show multiple
calendars depending on the resource and the calendar allocated to it ?
I can change the calendar for the reource but it doesn't make any difference
to the resource usage view.
I want to set up the Master as the resource pool, and therefore set plan 2
to use the resources from the Master.
This 'copies' the resources from Plan 2 into the Master - which is what I
want, however Plan 2 is based on a Sunday-Thursday working week ( jewish )
and the Master is standard UK ( Mon - Fri ).
When I pool my resources, the 'Resource Usage' view shows all resources on
the Jewish calendar - can I get the Resource Usage view show multiple
calendars depending on the resource and the calendar allocated to it ?
I can change the calendar for the reource but it doesn't make any difference
to the resource usage view.