Hi Jim,
Forget about master plans for a moment, you need a resource pool.
Create a new file and save it as "MyPool" (or any name you deem best) and
keeep it open.
Open each small plan, Tools, Resources, Share Resources, Use resources
from... MyPool
Save each small plan and your pool; close the lot.
Re-Open your pool with the third option (... pool and all sharers int one
master...)
There you are, you get a maste for free. Now you cna use leveling from teh
master file or from teh pool, whatever you prefer.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
Jim Lenahan said:
I want to roll multiple smaller plans into one master plan, and then
resource level from the master plan. I think I have to use one resource
pool in the master plan to do this. Any ideas on if this is right, or how
to do this??