Texasroy
I am working in 2007 pro desktop and find a feature that was available in
2003 has been changed. I have generic resources in my schedule and I now
know the actual individuals. After adding them to the resource sheet, I
choose the entire file and click on the Assign Resources icon, untending to
do a universal replace. In 2003 I could choose a generic and replace it with
the actual. In 2007, I cannot choose an individual resource withe the entire
file chosen, only when choosing individual tasks.