Resource Report Presentation to Upper Mgmt

M

Marilyn Campos

I have 6 projects with the same assigned resources. Each Project Manager is
not using the same naming convention and named the resources differently on
their individual projects even though they are the same 30 people. By
combining all 6 projects and renaming the resources to all be consistant I
see that the resources look duplicated. I don't know which ones to delete? I
need to provide what tasks are left to do on my 6 projects ,including late
tasks, with the named resources and exact durations by tomorrow. I am trying
to provide clarity for upper management in the simplest form and promote the
beneficial nature of that report. Please help?
 
R

Rod Gill

First you have to have consistent naming for each resource, change the
projects. This is a people training and process issue.

Second create a consolidation of all projects, but in the Insert Project box
make sure you Uncheck the Link option. Now all project's Tasks are copied to
the master file and all resources (with same spelling) are consolidated so
you can report across all projects.

This method does not update sub-projects if the master is changed (and vice
versa) but there are no permanent links that can corrupt files if PMs
rename, overwrite or move their project files.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
M

Marilyn Campos

Thank You Rod, What would be the best way (report)for me to provide the
labor file summaries by person by week please?
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top