D
Dee
I'm trying to create a report that shows how many employees vs contractors we
have assigned to specific tasks in a given month. I'm using MSP2007. I
created a export map to excel that allowed me to bring in the task name,
summary task name, start/end dates, resource names, and resource type (emp vs
con). The problem is when you create the pivot table, the data is counted
more than once. For example, a project is two months long, and a contractor
starts in month 1 and another starts in month 2 for a total of 2 contactors.
When you summarize the data, the total contractor number come out to three.
MSP is looking at the final finish date then summarizing from the earliest
start date.
Can anyone advise me on how to remedy this? Thanks!
have assigned to specific tasks in a given month. I'm using MSP2007. I
created a export map to excel that allowed me to bring in the task name,
summary task name, start/end dates, resource names, and resource type (emp vs
con). The problem is when you create the pivot table, the data is counted
more than once. For example, a project is two months long, and a contractor
starts in month 1 and another starts in month 2 for a total of 2 contactors.
When you summarize the data, the total contractor number come out to three.
MSP is looking at the final finish date then summarizing from the earliest
start date.
Can anyone advise me on how to remedy this? Thanks!