Resource updates

S

Sean

Janet:

Go to PWA and then select "Resources".. select Adjust
Actuals and then select the resource(s) whose time you
need to adjust... If you see a Gantt view,
select "timesheet" view from along the left pane.

Good Luck!

----------------------
EPM Solutions Group
Bennett Adelson
www.bennettadelson.com



-----Original Message-----
I have several resources who do the majority of their
work onsite. For whatever reason, they are having
problems using a VPN to access their calendars and cannot
update their task progress. Is there any way for me to do
this, other than going into the Gantt chart itself and
updating that. I have found, when I do that, PWA is not
updated.
 