I'm new to trying to use the resource allocation in Project. I have some
tasks which take a long time (like waiting for materials to arrive). If I
assign a resource to this task it appears to count their time during this
entire period. I can fake it out by reducing the %, but this method will get
complicated on a large plan where multiple resources are used.
Is there a way to devind the duration in time, and then estimate the total
hours a resource will be needed during that time?