Resource usage - how to seperate duration and hours?

N

New User

I'm new to trying to use the resource allocation in Project. I have some
tasks which take a long time (like waiting for materials to arrive). If I
assign a resource to this task it appears to count their time during this
entire period. I can fake it out by reducing the %, but this method will get
complicated on a large plan where multiple resources are used.

Is there a way to devind the duration in time, and then estimate the total
hours a resource will be needed during that time?
 
M

Mike Glen

Hi New User ,

Welcome to this Microsoft Project newsgroup :)

I would introduce a lag in the linking to cover the waiting time. Double
click on the task and add a duration in the Lag cell. Alternativerly,
introduce a new task for the delivery time and link its finish to the start
of the doing task.

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 
J

Jan De Messemaeker

Hi,

There are several ways to achieve this.

1. When assigning the resource, indicate the %
2. Insert a column "Work" and enter work before assigning the resource
3. When teh resource is aleady assigned, put the task type to fixed duration
and change the work value.
HTH
 