Resource Usage Report

R

Robin Roe

Hi

I need to generate a report that lists, by task, each resource's planned
hours for the next 3 months. I don't want to show tasks within that 3 months
that don't have any planned hours.

Thanks
 
J

John

Robin Roe said:
Hi

I need to generate a report that lists, by task, each resource's planned
hours for the next 3 months. I don't want to show tasks within that 3 months
that don't have any planned hours.

Thanks

Robin,
First of all I think you really want the Task Usage view, not the
Resource Usage view since you want the report by task. All you need is a
modified Date Range filter. Here is the process:

1. Go to Project/Filtered For/More Filters.
2. In the More Filters selection list find "Date Range..." and select it
3. Hit Edit
4. Add a third criteria to the filter as follows:
And/Or Field Name Test Value
And Work is greater than 0

5. Hit "OK" and "Apply"

Hope this helps.
John
Project MVP
 