S
Simha
Hi All
Click Resource Usage -> Format -> Details ->Work
On the timephased sheet or the right hand side of this view
I want to enter "Work' for each day.
PROBLEM:
When I enter 1 hr for particular task
for a given day MS Project enters 0s for next few days and enters
1hr.
When can this happen ?
What should I do to fix this ? so that I can enter the "Work" exactly the
day I want
Thanks all
Click Resource Usage -> Format -> Details ->Work
On the timephased sheet or the right hand side of this view
I want to enter "Work' for each day.
PROBLEM:
When I enter 1 hr for particular task
for a given day MS Project enters 0s for next few days and enters
1hr.
When can this happen ?
What should I do to fix this ? so that I can enter the "Work" exactly the
day I want
Thanks all