Resource Usage View Precision

M

MikeR

On the right hand side of the Resource Usage View, where it shows the
breakdown of hours by day,week,etc...

Is there a way to show the hours rounded to one or even no decimal places?
Any assistance on how to set that up, if its possible, would be great.

Thanks in advance.
 
C

Catfish Hunter

The only way I know of is to export to Excel. Then format cells and work in
Excel.
 
J

John

MikeR said:
On the right hand side of the Resource Usage View, where it shows the
breakdown of hours by day,week,etc...

Is there a way to show the hours rounded to one or even no decimal places?
Any assistance on how to set that up, if its possible, would be great.

Thanks in advance.

Mike,
Just a followup to Catfish's reply. You might want to take a look at the
"Analyze timescale data in Excel" utility/add-in found on the "Analysis"
toolbar. You will get slightly different results (i.e. format) by
exporting from either the Resource or Task Usage views. Of course with a
custom VBA macro, Project data can be exported and formatted in
virtually any form needed.

John
Project MVP
 