Hi,

I'm the owner of a Resource Pool to which ~25 files are attached to it. All
the work I do is through the Resource Pool file. I would like to know if it
is possible when looking at the Resource Usage View to "produce" a Gantt
Chart View for that specific resource rather then to have to consolidate all
the files and use the filters to look at the Gannt Chart of filtered resource?

Thank You.
 
R

Rod Gill

One way is to insert al projects into a new project but DON'T link (clear
the link option in the Insert Project dialog window). This copies all tasks
from all projects and consolidates all resource information. Now all you
need to do is filter for the resource in the Gantt Chart.

I record a macro of me creating this consolidation (be very careful about
clearing the link option) and then re-run the macro as needed. Once a week
records a great snapshot for the project.
 
B

Big_Bad_Yellow_Eskimo

Hi Rob,

Thanks a lot for the quick reply. I'm very impressed with the speed. So far,
I have posted 3 questions since yesterday and they all have been answered
(unfortunately not all problems fixed but I'm working on it!).
Now, what you are proposing me, I knew I could do it. The macro will speed
up the process BUT is it the only way to do it?

Thank You again.

Big_Bad_Yellow_Eskimo
 
J

Jan De Messemaeker

Hi Inuit,

Open your pool with the third option ("and all sharer files") and your
master project is there for the taking. No macro, standard Project.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Big_Bad_Yellow_Eskimo" <[email protected]>
schreef in bericht
 
A

AndyB

I Just used this little chestnut of info which has proven invaluable.
Thanks Jan.

AndyB
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Similar Threads

Resource Budget Cost - Tracking 0
Resource Usage Filters 8
Resource usage view 3
Resource Work Load 0
View Bar Icons 5
grouping or filtering tasks 5
Task Usage view 12
Gantt chart duration not showing 0

Top