Recurring tasks are a special case. They are marked with a priority of
1000, which means "do not level." When you first enter the recurring task
you need to include the time each one starts as well as the date the series
starts in the Start Date entry and make sure the times of the two tasks that
are giving you trouble don't overlap. You might have the 15 min daily
meeting start 14 Feb at 0900 and goes for X days while the weekly 1 hour
meeting starts 14 Feb at 1000 and goes for Y recurrences.
Recurring tasks are generally things like meetings that won't be scheduled
for our resource's convenience. If we have two of them going on at the same
time, he has to make a choice which one of them to go to. Leveling would
reschedule one of the meetings and that's not usually possible, hence
Project's behavior exempting them being moved by leveling.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs