How do I get the total cost of person's hrs for each task,subtaks, added to
total project instead of the cost of the durations/hrs based on the total
duration of all summary tasks together.
Ex:
Person work hrs (3hrtask +2hr task +3hr task) should not be equal to the
total work hrs of the summary task (inserted levelin delays,lag time and
other days in the middle). Cost should be $180.00 + $120.00+ $240.00
=$540.00 instead of $1,860.
Thanks to the forum I learned that " the duration of the summary task is
calculated based on the start of the earliest subtask to the latest subtask.
I understand that Project is also calculating the Work hours and cost columns
based on the same.
But what if I just want to identify the total cost of xperson hrs on all
tasks. How I do if as a consutant I want to charge hourly for the time spent
on all the tasks?
I checked in the resource sheet ,based on the standard rate, but it comes
with the same wrong total amount.
Thanks!
total project instead of the cost of the durations/hrs based on the total
duration of all summary tasks together.
Ex:
Person work hrs (3hrtask +2hr task +3hr task) should not be equal to the
total work hrs of the summary task (inserted levelin delays,lag time and
other days in the middle). Cost should be $180.00 + $120.00+ $240.00
=$540.00 instead of $1,860.
Thanks to the forum I learned that " the duration of the summary task is
calculated based on the start of the earliest subtask to the latest subtask.
I understand that Project is also calculating the Work hours and cost columns
based on the same.
But what if I just want to identify the total cost of xperson hrs on all
tasks. How I do if as a consutant I want to charge hourly for the time spent
on all the tasks?
I checked in the resource sheet ,based on the standard rate, but it comes
with the same wrong total amount.
Thanks!