S
stargurl549
Hi,
I'm trying to change my reosource's working time .. . I know you can
change the default working time from X-AM to Y-PM... but instead of doing
this time thing, is there a way to making the working time a certain number
of hours, throughout the entire project? So if "John" has 100 hours to work
on this project, total....
Thanks, i'd appreciate any help!
I'm trying to change my reosource's working time .. . I know you can
change the default working time from X-AM to Y-PM... but instead of doing
this time thing, is there a way to making the working time a certain number
of hours, throughout the entire project? So if "John" has 100 hours to work
on this project, total....
Thanks, i'd appreciate any help!