Resources as a percentage

S

SBakerNYC

I've been asked to total resources as a percent by hour by week.

Is this possible?
 
G

Gérard Ducouret

Hello,

View / Resource Usage
Right click on a yellow cell
Select Detail Styles...
In the "Available fields" list (lefthand) select Percent Allocation. OK
May be, hide the Work field.
Double click the time scale ans set the Bottom Tier units to Months (before
that you enlarged the Middle tier too)

Hope this helps,

Gérard Ducouret
 