Resourse Usage Summary View

E

E Carlsson

In most projects the summary level in the Resource Usage View presents the
timephased summary work in hours. However, in some projects, the summary
level of is presented in days. How can I change the view to display summary
work information of resources in hours?
 
J

John

E Carlsson said:
In most projects the summary level in the Resource Usage View presents the
timephased summary work in hours. However, in some projects, the summary
level of is presented in days. How can I change the view to display summary
work information of resources in hours?

E Carlsson,
When you say the "...summary level in the Resource Usage View...", I
assume you mean the Resource Name since that is the equivalent of the
"summary line" in that view. The dimension on Work field data is set by
Tools/Options/Schedule tab - Work is entered in.

John
Project MVP
 