Ressource calender

M

MAT

Hi..
I want that an enterprise Ressource work by a project just freidays and by
the others the whole week. is there a way to define such a calender or
should I do the plannning manuell, because I can not change the calender of
the enterprise calender in that way..
than you.
 
G

Gérard Ducouret

Hello MAT,

A resource can have only one calendar. But if this resource is the only one
assignment on each of his/her tasks, you can assign different calendars on
the tasks.

Hope this helps,

Gérard Ducouret
 