I
Ian Gray
Hi all,
I have a Master Schedule with 14 Sub-Projects. Each of the 14 Subprojects
are ultimately under my control but they each have a planner that will be
working on them day to day.
I will be saving the Baseline for all of the 14 + Master.
What I want to be able to do is revert back to this Baseline in the future,
should one of my planners do what they're NOT supposed to do and update the
baseline in their plan.
I'm sure this is possible, but I'm unsure how to achieve it... any
suggestions??
Thanks
I have a Master Schedule with 14 Sub-Projects. Each of the 14 Subprojects
are ultimately under my control but they each have a planner that will be
working on them day to day.
I will be saving the Baseline for all of the 14 + Master.
What I want to be able to do is revert back to this Baseline in the future,
should one of my planners do what they're NOT supposed to do and update the
baseline in their plan.
I'm sure this is possible, but I'm unsure how to achieve it... any
suggestions??
Thanks