meesh1224
I have some summary tasks in my plan that do not accurately reflect the sum
of the work in the detailed tasks. The tasks are baselined.
For example, I have 4 tasks that add up to 19 hours. This appears correctly
in the Work columns. In the Baseline Work column the sum is 119 hours. The
only thing I can think of is that I had some tasks in that grouping that I
removed and the baseline did not update to reflect the remaining tasks. Is
this expected behavior? If not, what should I be doing differently to update
the baseline if tasks are removed?
Is there something else I am missing?
Michelle
of the work in the detailed tasks. The tasks are baselined.
For example, I have 4 tasks that add up to 19 hours. This appears correctly
in the Work columns. In the Baseline Work column the sum is 119 hours. The
only thing I can think of is that I had some tasks in that grouping that I
removed and the baseline did not update to reflect the remaining tasks. Is
this expected behavior? If not, what should I be doing differently to update
the baseline if tasks are removed?
Is there something else I am missing?
Michelle