DavidR
We have a need to de-scope some work that was in the baseline. But I am not
allow to simply remove the task. I must keep the task in the project file.
I had hope I could just set the cost for those task to zero, select those
task and save the baseline using the “for selected task†option with the
rollup to summary task checked. But the math is not adding up. I change
$30K of scope to $0 but when I save the baseline the new baseline changes by
$37K and I can not figure out why. I only have the task that I set to $0
selected. Any ideas?
allow to simply remove the task. I must keep the task in the project file.
I had hope I could just set the cost for those task to zero, select those
task and save the baseline using the “for selected task†option with the
rollup to summary task checked. But the math is not adding up. I change
$30K of scope to $0 but when I save the baseline the new baseline changes by
$37K and I can not figure out why. I only have the task that I set to $0
selected. Any ideas?