G
gwdex
Hi, I'm new here but I have been using Project for quite awhile now and
have figured out many problems with it that I hope I can help others
with. Unfortunately, this problem has me stumped.
We are using Project 2007 to track our costs on a large construction
job.
We have had some changes made to our baseline cost. When I try to Set a
new baseline for the selected task, and have it roll up to the summary
tasks, the project is omitting one of the other tasks in the overall
project. This task is not included in the section that I am trying to
re-baseline.
Anyone have any ideas?
have figured out many problems with it that I hope I can help others
with. Unfortunately, this problem has me stumped.
We are using Project 2007 to track our costs on a large construction
job.
We have had some changes made to our baseline cost. When I try to Set a
new baseline for the selected task, and have it roll up to the summary
tasks, the project is omitting one of the other tasks in the overall
project. This task is not included in the section that I am trying to
re-baseline.
Anyone have any ideas?