Anyone else noticed this oddity ("undocumented feature") in Project Server
2003?

It seems that setting a group or individual Global Permissions Save Baseline
permission to "Deny" only prevents a person from setting "Baseline", but
allows a user to save Baselines 1 to 10 without any restrictions. I see both
adbvantages and drawbacks to this. It all depends on how you pitch it to
your user base. Anyway, if someone could validate that what I am seeing is
the same in other environments I would be interested to hear.
 
M

Mike Glen

Hi Sir Ganttalot,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
S

Sir Ganttalot

Thanks Mike. Indeed, I was of the impression that I had posted on the Server
group. I will repost it there. Any thoughts on the issue itself, BTW?

--
Sir Ganttalot

Coming soon to YouTube


Mike Glen said:
Hi Sir Ganttalot,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
M

Mike Glen

Sorry, I don't have a server.

Mike Glen
Project MVP


Sir Ganttalot said:
Thanks Mike. Indeed, I was of the impression that I had posted on the
Server
group. I will repost it there. Any thoughts on the issue itself, BTW?
 