I am trying to show schedule progress on a summary bar. For example if I
have 60 hours of work to do over a ten week period, and 30 of these hours are
scheduled to be done in the first four weeks, and I have completed 30 hours I
want my summary progress bar to be 40% of the total summary bar rather than
50%. Consequently if 30 hours were scheduled over the first nine weeks and
the remaining 30 hours were scheduled for week ten, I would want to show the
progress bar as 90% of the total summary bar rather than 50. I thought I
could use a summary progress bar which starts at [start] and ends at [%
complete] to do this, but it doesn't look right. Any help would be
aprreciated
have 60 hours of work to do over a ten week period, and 30 of these hours are
scheduled to be done in the first four weeks, and I have completed 30 hours I
want my summary progress bar to be 40% of the total summary bar rather than
50%. Consequently if 30 hours were scheduled over the first nine weeks and
the remaining 30 hours were scheduled for week ten, I would want to show the
progress bar as 90% of the total summary bar rather than 50. I thought I
could use a summary progress bar which starts at [start] and ends at [%
complete] to do this, but it doesn't look right. Any help would be
aprreciated