M
myranawabi
Hi,
Has anyone ever put together a schedule for Lab and its usage? Do w
add the Lab and its equipment as a resource? If so what type of
resource is it? It is neither work, cost, or material in my case.
Here is what I am facing. I need to put together a schedule for la
that is in use 7 days a week 24 hours. It will be used by multiple team
at different hours. Due to configuration limitations similar groups ca
share the lab while in other times the lab will be occupied exculsivel
by one team for so many days.
Having trouble with the logic currently. Oh to make matters worse eac
team is dependent on one another for delivery. their start and finishe
are dependent.
Can anyone help me? As anyone ever run into this before?
Thanks,
Myr
Has anyone ever put together a schedule for Lab and its usage? Do w
add the Lab and its equipment as a resource? If so what type of
resource is it? It is neither work, cost, or material in my case.
Here is what I am facing. I need to put together a schedule for la
that is in use 7 days a week 24 hours. It will be used by multiple team
at different hours. Due to configuration limitations similar groups ca
share the lab while in other times the lab will be occupied exculsivel
by one team for so many days.
Having trouble with the logic currently. Oh to make matters worse eac
team is dependent on one another for delivery. their start and finishe
are dependent.
Can anyone help me? As anyone ever run into this before?
Thanks,
Myr