P
PattiTechWriter
I am a Tech Writer who inherited a huge Project Schedule to maintain. I am
green when it comes to this tool and I could use all the help I can get!
Task 1 starts 10/11 and finishes 10/17, 5 days duration. Resource is "Don".
Task 2 starts and finishes 10/18, 1 day duration. Resource is "Don".
Task 3 starts 10/19 and finishes 10/21, 3 days duration. Resource is "Don".
When my boss runs a Resource Usage report,
for the week of 10/9, Don is scheduled for 2 hours, not 32; and
for the week of 10/16, he is scheduled for 8 hours, not 40.
When you look at the Schedule, things are peachy. But when my boss looks at
usage, he wants to know what Don is doing all day! I don't know why the
usage numbers are different than the Schedule.
Can anyone help?
Patti
green when it comes to this tool and I could use all the help I can get!
Task 1 starts 10/11 and finishes 10/17, 5 days duration. Resource is "Don".
Task 2 starts and finishes 10/18, 1 day duration. Resource is "Don".
Task 3 starts 10/19 and finishes 10/21, 3 days duration. Resource is "Don".
When my boss runs a Resource Usage report,
for the week of 10/9, Don is scheduled for 2 hours, not 32; and
for the week of 10/16, he is scheduled for 8 hours, not 40.
When you look at the Schedule, things are peachy. But when my boss looks at
usage, he wants to know what Don is doing all day! I don't know why the
usage numbers are different than the Schedule.
Can anyone help?
Patti