Scheduled OLAP build. Fixed Date Range doesn't match

J

John

Hi,

My OLAP Cube building works FINE with "Fixed Date Range" options when using
the Update Now button.

But when I use "Fixed Date Range" options with scheduling (e.g. "Update
every 1 days"...), the date range doesn't match in my OLAP Cube.

Is that common feature ;) in the P2002 environment?

Thanks for help,
John M
 
M

Michael

John,

There is hot fix out for this. Check KB article #817837. You will
have to contact Microsoft to get it.

Thanks,

Michael
 