N
Ndigitman
I have five one day tasks in phase A, three one day tasks and two two days
tasks in phase B. Phase A is two weeks fixed duration and Phase B is three
weeks fixed duration. Each task within phase A are independent of each other
and can start in any order. Each task within phase B has to occur in
sequence starting with the first task. Understand that all of the tasks
within each phase add up to less than the duration of the phase. How can I
represent this in MS project?
tasks in phase B. Phase A is two weeks fixed duration and Phase B is three
weeks fixed duration. Each task within phase A are independent of each other
and can start in any order. Each task within phase B has to occur in
sequence starting with the first task. Understand that all of the tasks
within each phase add up to less than the duration of the phase. How can I
represent this in MS project?