F
FrankH
Using Project 200 I am trying to show the effect of a short, daily, task on
project schedules but leveling is not working as expected.
I want to schedule a 2 hour admin task to a resource for each day of the
project. I want this resources other tasks to be scheduled into the
remaining hours in of the day. In practice, this task my not be necessary
some days and other days it may take more than 2 hours. Initially, I want to
see what effect this task has on project deadlines but once the project is
underway I want to be able to track the impact of these variations.
I have tried setting up a recurring task but MS Project will not schedule
tasks into the remaining hours, they are just pushed out to the end date for
the recurring task. I have tried scheduling the entire project in hours and
I have checked the 'Leveling can make splits in remain tasks' option in
Resource leveling. I have also tried reducing the recuring task priority
level but with no success.
I would be grateful for any suggestions.
project schedules but leveling is not working as expected.
I want to schedule a 2 hour admin task to a resource for each day of the
project. I want this resources other tasks to be scheduled into the
remaining hours in of the day. In practice, this task my not be necessary
some days and other days it may take more than 2 hours. Initially, I want to
see what effect this task has on project deadlines but once the project is
underway I want to be able to track the impact of these variations.
I have tried setting up a recurring task but MS Project will not schedule
tasks into the remaining hours, they are just pushed out to the end date for
the recurring task. I have tried scheduling the entire project in hours and
I have checked the 'Leveling can make splits in remain tasks' option in
Resource leveling. I have also tried reducing the recuring task priority
level but with no success.
I would be grateful for any suggestions.