J
John Nurick
G'day all,
Does Project 2003 have a way of specifying that a task can only be done at
certain times of year? E.g.
Task: Install ski lift
Can't be started before task XXX is completed
Duration: 50 days
Constraint: Site is only accessible between 1 June and 20 October, so if
work can't
start by 1 August in year N it has to be put off until 1 June in year
N+1
If not, suggestions for a work-round will be welcome.
Does Project 2003 have a way of specifying that a task can only be done at
certain times of year? E.g.
Task: Install ski lift
Can't be started before task XXX is completed
Duration: 50 days
Constraint: Site is only accessible between 1 June and 20 October, so if
work can't
start by 1 August in year N it has to be put off until 1 June in year
N+1
If not, suggestions for a work-round will be welcome.