Hi McGeeky ,
Welcome to this Microsoft Project newsgroup
There isn't a recognized method to record original Durations, but if you
want to enter all the tasks first and then save a Baseline before you add
resources, then you have such information. However, Baselines are designed
to be used when you have finished planning you project whence you save the
Baseline for later comparisons. You could use a custom filed to record the
originals.
FAQs, companion products and other useful Project information can be seen at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for Project Tutorials
wrote: